Search Results
San Bruno garage closed in stages for lighting improvements starting April 26, 2021
On Monday, April 26, 2021, the garage at San Bruno Station will be closed in stages for approximately nine weeks to allow our contractor to retrofit and upgrade the garage lighting. The garage will be closed in stages starting with floors 3-5. Once those floors are completed, the first and second floors will
16th St. Mission Station elevator out of service November 14 to December 16, 2022
UPDATE: December 13, 2022 The street level elevator is now back in service. UPDATE: November 23, 2022 The street level elevator is now expected to be back in service on December 16th due to delays involving a third party. Crews are working seven days a week on this project to get this unit up and running with
Richmond Station garage closures for lighting improvements starting 4/26
Beginning Tuesday, April 26, 2022, the garage at Richmond Station will be closed in phases for approximately seven weeks to allow our contractor to retrofit and upgrade the garage lighting. Levels 3-6 will remain open during Phase 1 of the project. Levels 1 and 2 will be open during Phase 2 (see map). ADA
Elevator out of service at 24th St. Mission Station 6/14/21-7/22/21
UPDATE: July 19, 2021 The new projected return to service date for the 24th St. Mission street level elevator is July 22, 2021. The delay was caused by severe corrosion discovered during the door replacement project. The corrosion requires crews to chip out the existing concrete, reinstall new brackets under
Dublin/Pleasanton Station garage closed for lighting improvements starting 9/7
On Tuesday, September 7, 2021, the garage at Dublin/Pleasanton Station will be closed in phases for approximately eight weeks to allow our contractor to retrofit and upgrade the garage lighting. Level 1 will remain open during Phase 1 of the project. Levels 2-4 will be open during Phase 2. Surface lots will
South San Francisco Station garage closed for lighting improvements starting 8/30
On Monday, August 30, 2021, the garage at South San Francisco Station will be closed for approximately six weeks to allow our contractor to retrofit and upgrade the garage lighting. Levels 2-4 will remain open during Phase 1 of the project. Level 1 will be open during Phase 2. Surface lots will also remain
MacArthur Station garage closed in phases for lighting improvements starting 12/7/2021
On Tuesday, December 7, 2021, the garage at MacArthur Station will be closed in phases for approximately five weeks to allow our contractor to retrofit and upgrade the garage lighting. During Phase 1, floors 1 and 2 of the garage will be closed with parking available on floors 3 and up. Once floors 1 and 2
Access impacts expected at North Berkeley Station from work on raised crosswalk
Work is scheduled to begin on July 5, 2022, on a raised crosswalk in front of the North Berkeley Station. Work will take place directly in front of the station entrance (see map). This is the latest step for the North Berkeley Access Improvements Project. Construction impacts will include the following
Temporary relocation of bike lockers at Daly City due to earthquake safety work
Dear Customer: As part of our system-wide Earthquake Safety Program, we have begun strengthening structures at the Daly City Station to withstand future earthquakes. The work requires temporary relocation of some of the bicycle lockers and bicycle racks. Lockers and racks will be closed on Monday, August 9
City of El Cerrito paving project to affect parking at stations
On Monday, September 28th, the City of El Cerrito (City) began its citywide street repaving project that will affect street parking nearby the El Cerrito del Norte and El Cerrito Plaza stations. City staff has advised BART that the repaving project is a two-step process that will prohibit parking on the