Bay Fair Station: Accessibility Improvements- 2023/2024
UPDATE December 29, 2023
The next phase of work at Bay Fair will start on January 15th and will last 4 weeks. During construction, all pedestrian detours will be accessible. Construction will take place in two locations (see map below):
- In the passenger loading zone, the accessible loading zone will be replaced and the regular pathway to the passenger loading zone will be blocked by fencing. To get to the passenger loading walk through the bus area, towards Bus Bay C1. A temporary crosswalk will be provided from there to the passenger loading zone.
- On the pathway towards the Bayfair Center. A segment of sidewalk will be replaced between the station and the first crosswalk. A pedestrian detour will be provided from the station elevator, across a small parking area, and around a landscaped area to connect to the existing crosswalk.
No construction will take place in the bus area during this phase.
The Accessibility Improvement Program (AIP) will improve accessibility in and around BART stations to better meet the needs of people with disabilities, including replacement or upgrade of ramps, sidewalks and accessible paths, bus and passenger loading zones, as well as handrails, wall protrusion detection, wheelchair-accessible phones, TTY devices, courtesy phones, and elevator lobby lighting.
The entire project will be done in phases with full completion by Spring 2024. Thank you for your patience as we work to improve access to the BART Station.
UPDATE December 7, 2023:
Construction for the next phase of the Bay Fair Station Accessibility Improvements Project will begin on Friday, December 8, 2023 and last for approximately 3 weeks.
During this phase, buses will return to their permanent locations (see list below for locations and map below). Construction will take place on sidewalks in the parking lot just south of the Police substation. All pedestrian detours will be ADA accessible.
AC Transit buses and shuttles will be located to the following bus bays.
- Line 10 to Hayward BART: A2
- Line 10 to San Leandro BART: A1
- Line 28 to Hayward BART: A4
- Line 28 to San Leandro BART: B3
- Line 35 to Juvenile Justice Center: C2
- Line 35 to Foothill Square: C3
- Line 40: B2
- Line 93: A3
- Line 97: A6
- Line 706: B1
- Line 801 to Fremont BART: A2
- Line 801 to San Leandro BART: A1
- Alameda County Sustainability Shuttle: C4
- San Leandro Flex Rides: C4
Temporary wayfinding signage will be posted to direct customers.
The Accessibility Improvement Program (AIP) will improve accessibility in and around BART stations to better meet the needs of people with disabilities, including replacement or upgrade of ramps, sidewalks and accessible paths, bus and passenger loading zones, as well as handrails, wall protrusion detection, wheelchair-accessible phones, TTY devices, courtesy phones, and elevator lobby lighting.
The entire project will be done in phases with full completion by Spring 2024. Thank you for your patience as we work to improve access to the BART Station.
UPDATE November 9, 2023:
Construction for the next phase of work on the Bay Fair Station Accessibility Improvements Project will begin on Thursday, November 16, 2023 and last for approximately 3 weeks.
During this second phase, bus bays B1, B2, B3, and C4, will be closed. All pedestrian detours will be ADA accessible. AC Transit buses and shuttles will be relocated to Bus Aisle A and Bus Aisle C as follows:
- Line 10 to Hayward BART: A2
- Line 10 to San Leandro BART: A1
- Line 28: A4
- Line 35: C3
- Line 40: B4
- Line 93: A3
- Line 97: C1
- Line 706: A0
- Line 801 to Fremont BART: A2
- Line 801 to San Leandro BART: A1
- Alameda County Sustainability Shuttle: A0
- San Leandro Flex: A0
Temporary wayfinding signage will be posted to direct customers. All pedestrian detours will be accessible.
The Accessibility Improvement Program (AIP) will improve accessibility in and around BART stations to better meet the needs of people with disabilities, including replacement or upgrade of ramps, sidewalks and accessible paths, bus and passenger loading zones, as well as handrails, wall protrusion detection, wheelchair-accessible phones, TTY devices, courtesy phones, and elevator lobby lighting.
The entire project will be done in phases with full completion by Spring 2024. Thank you for your patience as we work to improve access to the BART Station.
NOTE: The information below was originally posted on October 6, 2023
Construction for the first phase of the Bay Fair Station Accessibility Improvements Project will begin on Monday, October 16, 2023 and last for approximately 5 weeks.
During this first phase, the first aisle of buses (shown in map as Aisle A), will be closed. Pedestrian access to Elgin Street, south of the station, will be available by walking down Bus Aisle B. The pedestrian detour will be ADA accessible. AC Transit buses will be relocated to the Bus Aisle B and Bus Aisle C as follows:
- Line 10 to Hayward BART: B3
- Line 10 to San Leandro BART: B2
- Line 28: B1
- Line 35: C3
- Line 40: B4
- Line 93: A0
- Line 97: C1
- Line 706: B1
- Line 801 to Fremont BART: B3
- Line 801 to San Leandro BART: B2
The Alameda County Sustainability Shuttle will remain in its current location of Bus Bay C4. Temporary wayfinding signage will be posted to direct customers.
The Accessibility Improvement Program (AIP) will improve accessibility in and around BART stations to better meet the needs of people with disabilities, including replacement or upgrade of ramps, sidewalks and accessible paths, bus and passenger loading zones, as well as handrails, wall protrusion detection, wheelchair-accessible phones, TTY devices, courtesy phones, and elevator lobby lighting.
The entire project will be done in phases with full completion by Spring 2024. Thank you for your patience as we work to improve access to the BART Station.