Pre-construction work at Pleasant Hill BART Station Transit Village
Contra Costa County approved the final development plan for the Pleasant Hill BART Station Transit Village in May 2005. The complex is being developed by Pleasant Hill Transit Village Associates, a partnership of Avalon Bay Communities and Millennium Partners. It will be a mixed-use project that incorporates office space, retail, and residential units. The Transit Village will be constructed on existing BART parking lots.
Developers anticipate starting pre-construction work for the BART Parking Structure Addition in late February 2006. A nine-level addition to the existing parking garage will provide replacement parking for spaces that will be displaced by the Transit Village. Construction will take approximately 18-24 months.
In preparation for the construction, the following activities will occur during the next two months:
- Construct new basement stairs.
- Relocate reserved parking.
- Relocate passenger drop-off/pickup areas.
- Relocate accessible parking on the North side of the Station.
- Prepare patron assisted parking lot.
- Implement patron assisted parking.
Detailed information will be provided in the future before the activities begin.
If you have any questions about this Passenger Bulletin, please call 510.464.6235.