Statement regarding February letter from the Federal Transit Administration (FTA)

BARTtv: Video of BART's response

BART has received FTA Administrator Peter Rogoff’s letter today stating that the FTA has rejected BART’s plan to meet the FTA’s standards of full compliance with Title VI of the Civil Rights Act. This letter cites no substantive deficiencies in BART’s latest draft action plan to correct Title VI deficiencies identified in a December 2009 audit. Instead, the basis of the FTA Administrator’s rejection rests solely on the fact that BART’s plan contains a timetable with an end date beyond September 30, 2010—the deadline for awarding stimulus fund grants.

BART’s original draft action plan, which was submitted to the FTA on January 28th committed to complete all required tasks well before September 30, 2010, but following its review, FTA staff directed BART to plan for a longer timetable.

Additionally, today’s letter from the Administrator referred to a September 30 funding disbursement deadline. The Federal Register (Vol. 79, No. 42) of March 5, 2009 states that ARRA funds need only to be awarded to specific project by that date. Grant recipients have five years to draw down—or  spend—these federal funds.

“BART is extremely disappointed and dismayed that FTA will not use its discretion to allow stimulus funding to the Oakland Airport Connector while BART is working to remedy Title VI deficiencies,” said BART General Manager Dorothy W. Dugger. “BART’s commitment to Title VI and Civil Rights is strong and abiding and we are fully committed to completing and correcting any deficiencies in our program. The action plan we submitted to FTA makes that clear.

Under Title VI implementation regulations, the enforcement of Title VI relies on voluntary curing of deficiencies with the denial of funding as a final, not first, step in the process.
“Longtime opponents of this project are using the Civil Rights Act to stop the Oakland Airport Connector project and the thousands of jobs it will bring to this region, many of which would be held by minority workers. Access to jobs is also a Civil Rights issue,” said BART General Manager Dorothy W. Dugger. “The Oakland Airport Connector contractor has committed that 20 percent of the construction work and 33 percent of the professional services work will go to Disadvantaged Business Enterprises.”

The FTA does not cite any deficiencies in our last action plan other than it contains a timetable with an FTA-imposed deadline of September 30, 2010.

BART is fully committed to completing and executing a final plan to FTA’s satisfaction.

PROJECT COST $60M LESS THAN EXPECTED
The total cost of the project is $492 million – or $60 million less than the $552 million BART estimated in April 2009.  A competitive bidding environment led to lower than projected costs.

OAC DOES WHAT STIMULUS FUNDS ARE DESIGNED FOR
The OAC project does exactly what Congress asked of Stimulus funded projects - and that is it will create between 2,500 and 5,200 job opportunities for the area, which are of vital importance to the region’s economic recovery. These include jobs in the construction, electrical, steel fabrication and other building trades that are experiencing unemployment rates in excess of 30 percent.  The OAC will also leave a legacy transit connection that would carry thousands of daily riders to the Oakland regional airport, on time and without pollution and traffic congestion.  Finally, the project is aimed to significantly enhance the airport’s national prestige as one of the few in the country with a coveted world-class, transit connection, which will allow the airport to attract the businesses that will help drive the East Bay’s future economic growth.

WIDESPREAD SUPPORT FOR CONNECTOR PROJECT
On January 20, BART officials held a news conference to respond to the FTA’s January 15 Title VI letter and announced their commitment to meet FTA requirements.  A broad coalition of advocates joined BART officials to voice their support of the project.  Oakland Mayor Ron Dellums, the Alameda County Transportation Improvement Authority, Omar Benjamin, the Executive Director of the Port of Oakland, Andreas Cluver, Secretary-Treasurer of the Building and Construction Trades Council of Alameda County and Andy Slivka, Jr., Marketing and Political Representative of the Carpenters Union 713 Alameda County are examples of local leaders in support of OAC.

Coalition in Support of the Oakland Airport Connector Project:

Congresswoman Barbara Lee
Congressman Jerry McNerney
Mayor Ron Dellums
Oakland City Council
Oakland Port Commission
Metropolitan Transportation Commission
Alameda County Congestion Management Authority
Alameda County Transportation Improvement Authority
Assembly Member Sandre Swanson
Bay Area Council
Oakland Chamber of Commerce
Oakland Branch NAACP
Chinatown Chamber of Commerce
Oakland African American Chamber of Commerce
San Francisco Black Chamber of Commerce
Hispanic Chamber of Commerce
Cypress Mandella Partnership
100 Black Men
Pastor Earl Crawford, frmr President CA State Baptist Convention
Unity Council
Airport Area Business Association
Former City Council members and Port Commissioners Henry Chang and Dick Spees
ABAG Executive Director Henry Gardner
All airlines doing business at the Oakland International Airport
Bay Area Business Coalition
Alameda County Building Trades Council and all its affiliates – Operating Engineers, Laborers, Carpenters, Ironworkers, etc
IBEW Local 595
California Alliance for jobs
Oakland Visitors and Convention Bureau
Oakland Association of Black Trade and Trade
East Bay Small Business Council
Walnut Creek Chamber of Commerce
Association of General Contractors
Oakland Post Newspaper – Editor Paul Cobb

To view video of a press conference discussing BART's response to the FTA's letter, go to BARTtv